    Hydropower, Crown Hydro, Upper St. Anthony Falls Lock and Dam

    The Federal Energy Regulatory Commission (FERC) issued license 11175 to Crown Hydro, LLC, in 1999 which granted it the exclusive rights to develop a hydropower facility in the Mill Ruins Park area on the Mississippi River near Upper St. Anthony Falls Lock and Dam in Minneapolis, Minnesota. The Crown Hydro Project was originally proposed to be located in the Crown Roller Building and then, later, on Minneapolis park land. Crown Hydro was unable to secure the needed real estate agreements with the Minneapolis Park and Recreation Board. In 2013, Crown Hydro made a proposal to locate the project on Corps-managed Government land at Upper St. Anthony Falls Lock and Dam. The total 3.4-megawatt estimated capacity would be enough to provide power to more than 2,300 households.