    Operations & Maintenance: Lake Traverse Repairs Modernization Project

    The St. Paul District staff has been conducting field investigations, developing hydrologic and hydraulic models and developing plans and specifications for the three sites as well as the water control manual update. The White Rock Dam modernization project will be ready for contract award in May 2025. The Reservation Dam and Browns Valley Dike work will be completed and awarded in 2025. The Water Control Manual update will be complete in 2025.