This work will determine whether continued operation and ownership of Lower St. Anthony Falls Lock and Dam and Lock and Dam 1 are in the federal interest, and if not, consider alternatives for disposal of the property.
Published: 4/21/2025
This work will determine whether continued operation and ownership of the Upper St. Anthony Falls Lock project is in the federal interest, and if not, consider alternatives for disposal of the property.
Published: 4/21/2025
The purpose of the Pool 2 Dredged Material Management Plan is to prepare a coordinated long-term plan for managing dredged material in Pool 2. This plan was initiated due to increases in dredging volumes throughout Pool 2. Furthermore, three temporary placement sites for dredged material need to be excavated in Lower Pool 2.
Published: 4/25/2025
The U.S. Army Corps of Engineers operates and maintains the Upper Mississippi River 9-Foot Channel Navigation Project, and one method the U.S. Army Corps of Engineers uses to keep the channel the right size is dredging river soils or “material.”
The purpose of the Dredged Material Management Plan is to prepare a coordinated, long-term plan for managing dredged material in Pool 3 and Upper Pool 4. This plan was initiated due to needs for dredged material management upland placement sites.
Published: 4/24/2025
The U.S. Army Corps of Engineers operates and maintains the Upper Mississippi River 9-Foot Channel Navigation Project, and one method used to maintain the 9-foot channel is dredging river soils or “material.” The purpose of the Pool 9 Dredged Material Management Plan is to prepare a coordinated long-term plan for managing dredged material in Pool 9. This plan was initiated due to needs for dredged material management at upland placement sites, especially in the upstream reach of the pool.
Published: 4/21/2025
This embankment rehabilitation project addresses restoring embankments to meet current design standards. Overtopping protection adjacent to concrete structures is the priority for design and construction efforts; no increase in the height of the embankments is planned.
Published: 4/17/2025
Locks and Dams 2 through 10 have used the same miter gates since their construction in the 1930s. Over time, the gates have been damaged and distressed, leading to serviceability and safety issues. This project will replace the gates and upgrade the anchorage systems, increasing navigational longevity and operational readiness while decreasing repair costs and downtime due to maintenance or failure.
Published: 4/17/2025
A draft Problem Appraisal Report completed in 2017 found that complete riprap overlay of the embankments to rehabilitate rock degradation was not economically justified but that there are other opportunities to improve scour resilience while improving the ecosystem. Some options include creating upstream berms, creating islands to reduce wave fetch, and providing submergible segments with crest superiority at some dams.
Published: 4/17/2025
The tow rail system is integral to the operation of Mississippi River Locks and Dams 2 through 10. At each lock, a tow rail system is attached to the top of the lock guidewall to help guide tows through the lock chamber. The tow rail systems of Locks and Dams 2 through 10 have been deteriorating over the past several years, requiring rehabilitation of these systems.
Published: 4/21/2025
Locks and Dams 3 through 10 have auxiliary chambers. Each auxiliary chamber has only a single set of miter gates that could pass shallow draft navigation traffic if the lock chamber was out of operation and the upstream and downstream pools were equalized. At each site, the U.S. Army Corps of Engineers only installed one set of miter gates. An auxiliary lock chamber was never authorized by Congress, which would have included a second set of miter gates. Since installation, the auxiliary emergency gates have never been used, and the gate operating machinery was never installed.
Published: 9/12/2016
The Navigation and Ecosystem Sustainability Program (NESP) seeks to provide a safe, reliable, cost-effective and environment-sustainable waterborne navigation system by implementing switchboats at five locks and constructing mooring cells and seven new 1,200-foot locks. NESP will restore the aquatic and terrestrial habitat to a more natural condition on more than 100,000 acres throughout the system through a wide variety of ecosystem projects.
Published: 4/25/2025
The Fountain City Service Base Building 9 Replacement Project is a two-phase project to improve the function and safety throughout the service base. The two objectives of the project are to replace the deteriorated mooring dolphins on the west side of the Fountain City harbor channel and modernize the service base.
Published: 4/28/2025
The Fountain City Service Base Sustainment and Modernization Project is a two-phase project to improve function and safety throughout the service base. The two objectives of the project are to replace the deteriorated mooring dolphins on the west side of the Fountain City harbor channel and modernize the service base.
Published: 4/17/2025
The Lock Guidewalls-Distress Repair Recommendations project for Locks and Dams 2 through 10 has been ongoing since the mid-1990s. The purpose of the end cell projects is to extend the longevity of each site and to reduce operability issues and required maintenance
Published: 4/17/2025
In 2017, a hydraulic study was launched to identify potential causes of the increased outdraft at Lock and Dam 7 and to investigate and implement measures to alleviate the condition. Flow measurements collected over the last 30 years indicate a significant shift in flows just upstream of Lock and Dam 7, with nearly 20% more flow coming through the existing navigation channel, which must then exit through the dam, exacerbating the outdraft condition.
Published: 4/17/2025
Maintenance of dam spillway gates are required to avoid degradation and eventual replacement. Cost analyses show it is economically favorable to maintain these gates rather than replace them. There are also reliability and safety concerns with allowing the gates to degrade to the point that they must be replaced.
Published: 4/16/2025
The U.S. Army Corps of Engineers is responsible for maintaining a 9-foot navigation channel as an important component of the inland navigation system.
Published: 4/15/2025
Section 14 of the Rivers and Harbors Act of 1899 authorizes the Secretary of the Army to grant permission for alterations to existing U.S. Army Corps of Engineers (USACE) projects under certain circumstances. The authority is codified in 33 U.S. Code 408. Section 408 provisions apply to works that were built by USACE and are locally maintained, such as local flood control projects, and works that are operated and maintained by USACE, such as locks and dams. Proposals submitted for Section 408 review and approval undergo a rigorous engineering, policy and environmental review by USACE and, if required, independent external peer review.
Published: 4/16/2025
Navigation and Ecosystem Sustainability Program (NESP) is a long-term program of ecosystem restoration and navigation improvements for the Upper Mississippi River System (UMRS). NESP will improve system capacity and reduce commercial traffic delays through construction of seven new 1,200-foot locks, mooring cells, and switchboat implementation.
Published: 12/2/2020
The Navigation and Ecosystem Sustainability Program is a long-term program of ecosystem restoration and navigation improvements for the Upper Mississippi River System. Johnson Island is located near Trempealeau, Wisconsin, in Pool 6 of the Mississippi River. Island erosion, island dissection, and sedimentation have greatly reduced the quality and quantity of terrestrial and aquatic habitat in the project area. Project objectives are directed at improving conditions for fish, aquatic and terrestrial wildlife, maintaining emergent vegetation, maintaining submersed vegetation and island stabilization and nourishment to restore connectivity, and promotion of floodplain forest regeneration.
Published: 4/16/2025
This Navigation and Ecosystem Sustainability Program study is a partnership with the National Park Service, U.S. Fish and Wildlife Service, Iowa Department of Natural Resources, Wisconsin Department of Natural Resources, and U.S. Army Corps of Engineers. The study will consider alternatives including riverbank stabilization and protection, floodplain restoration, closure or partial closure structures, and in-channel diversion structures.
Published: 4/16/2025
The primary purpose of this project is to address general degradation of habitat quality due to sediment deposition, wind-driven wave action, declining bathymetric diversity, and a decline in aquatic vegetation. Concerns over habitat deficiencies in Upper Pool 4 include reduced habitat diversity and quality, lack of aquatic vegetation and invertebrates, and reduced abundance of fish and wildlife.
Published: 4/16/2025
Concerns over habitat deficiencies in Wacouta Bay, most resulting from sedimentation and turbidity, include reduced aquatic and terrestrial habitat diversity and quality, lack of aquatic vegetation, lack of protected wetlands, and reduced abundance of fish and wildlife. The Wacouta Bay project is a Navigation and Ecosystem Sustainability Program study that will consider alternatives including island building and enhancement, forest enhancement and creation, backwater restoration and dredging, island and shoreline protection, and use of dredged material.
Published: 4/16/2025
The U.S. Army Corps of Engineers St. Paul District is responsible for maintaining 244 miles of the Upper Mississippi River 9-foot channel navigation system. The navigation project within the St. Paul District includes 13 locks and dams that are operated and maintained by the U.S. Army Corps of Engineers.
Published: 4/21/2025
The St. Paul District is responsible for maintaining 244 miles of the Upper Mississippi River 9-Foot Channel Navigation Project for inland navigation.
Published: 4/21/2025