DN 16-11                                            DREDGING NOTICE

                                               U.S. ARMY CORPS OF ENGINEERS

                                                            ST. PAUL DISTRICT

 

NOTICE DATE: June 29th, 2016                                DREDGING CATEGORY: Imminent

MEETING DATE: If requested                                  MEETING TIME:

BOAT REQUIREMENT:                                           MEETING LOCATION:

DREDGE CUT NAME: Homer                                 RIVER MILE: 720.0 – 720.8

                                                                       

HISTORIC DATA

Frequency:  24%                                            Avg. Quantity/Job:  27,783 yd3

Date Last Dredged: June 8th, 2015                 Avg. Quantity/Year:  7,122 yd3

 

SURVEY DATA

Date Surveyed: June 24th, 2016

Water Surface Elevation: 645.1

Low Control Pool Elevation: 644.2

Net Difference: + 0.9’

5-Day River Forecast: Slow decline

 

DREDGING DATA

Recommended Channel Width: 300 feet

Recommended Dredging Depth: 12 feet

Estimated Quantity: 17,128 yd3

Type of Dredge: Contract Mechanical

Proposed Dredging Date: June 29th, 2016

Estimated Duration: 9 dredging days

Justification for Dredging: The navigation channel is reduced to 240 feet between the 9.0’ contours and reduced to 120 feet between the 10.5’ contours.

 

MATERIAL PLACEMENT DATA

Proposed Placement Site: Winona Technology Park

Location: 6-722.9-RMP

Site Characteristics: The material will be unloaded at the East End Boat Harbor at 723.6 RDB and trucked to Winona Technology Park which is a short term site provided by the Winona Port Authority. The Winona Port Authority has obtained all necessary permits for this action. 

 

If you have any questions concerning this project, or if you would like to request an on‑site meeting, please contact aChannel Maintenance Coordinator at (651) 290-5155.

 

 

 


Dredge Notice 16-11 Homer

Published June 29, 2016

DN 16-11                                            DREDGING NOTICE

                                               U.S. ARMY CORPS OF ENGINEERS

                                                            ST. PAUL DISTRICT

 

NOTICE DATE: June 29th, 2016                                DREDGING CATEGORY: Imminent

MEETING DATE: If requested                                  MEETING TIME:

BOAT REQUIREMENT:                                           MEETING LOCATION:

DREDGE CUT NAME: Homer                                 RIVER MILE: 720.0 – 720.8

                                                                       

HISTORIC DATA

Frequency:  24%                                            Avg. Quantity/Job:  27,783 yd3

Date Last Dredged: June 8th, 2015                 Avg. Quantity/Year:  7,122 yd3

 

SURVEY DATA

Date Surveyed: June 24th, 2016

Water Surface Elevation: 645.1

Low Control Pool Elevation: 644.2

Net Difference: + 0.9’

5-Day River Forecast: Slow decline

 

DREDGING DATA

Recommended Channel Width: 300 feet

Recommended Dredging Depth: 12 feet

Estimated Quantity: 17,128 yd3

Type of Dredge: Contract Mechanical

Proposed Dredging Date: June 29th, 2016

Estimated Duration: 9 dredging days

Justification for Dredging: The navigation channel is reduced to 240 feet between the 9.0’ contours and reduced to 120 feet between the 10.5’ contours.

 

MATERIAL PLACEMENT DATA

Proposed Placement Site: Winona Technology Park

Location: 6-722.9-RMP

Site Characteristics: The material will be unloaded at the East End Boat Harbor at 723.6 RDB and trucked to Winona Technology Park which is a short term site provided by the Winona Port Authority. The Winona Port Authority has obtained all necessary permits for this action. 

 

If you have any questions concerning this project, or if you would like to request an on‑site meeting, please contact aChannel Maintenance Coordinator at (651) 290-5155.