DN 20-27 DREDGING NOTICE
U.S. ARMY CORPS OF ENGINEERS
ST. PAUL DISTRICT
NOTICE DATE: July 10th, 2020 DREDGING CATEGORY: Imminent
MEETING DATE: If requested MEETING TIME:
BOAT REQUIREMENT: MEETING LOCATION:
DREDGE CUT NAME: Petersons Bar RIVER MILE: MN River 11.7 – 12.6
HISTORIC DATA
Frequency: 60% Avg. Quantity/Job: 18,371 yd3
Last Date Dredged: Sept. 12th, 2019 Avg. Quantity/Year: 11,023 yd3
SURVEY DATA
Date Surveyed: July 6th, 2020
Water Surface Elevation: 694.4
Low Control Pool Elevation: 686.8
Net Difference: +7.6’
5 Day River Forecast: steady decline
DREDGING DATA
Recommended Channel Width: 100 feet
Recommended Dredging Depth: 11 feet
Estimated Quantity: 30,343 yd3 plus 412 yd3 placement site access
Type of Dredge: Contract Mechanical Plant 3
Proposed Dredging Date: July 14th, 2020
Estimated Duration: 15 dredging days
Justification for Dredging: The navigation channel is closed to the 9.0’ contours once the water levels get down to Low Control Pool.
MATERIAL PLACEMENT DATA
Proposed Placement Site: Cargill East River
Location: MN-14.1-RMP
Site Characteristics: This is an upland beneficial use stockpile site provided to the Corps by the Lower MN River Watershed District.
If you have any questions concerning this project or want to request an on‑site meeting please call a dredging manager at (651) 290-5155.