DN 15-35 DREDGING NOTICE
U.S. ARMY CORPS OF ENGINEERS
ST. PAUL DISTRICT
NOTICE DATE: September 28th, 2015 DREDGING CATEGORY: Imminent
MEETING DATE: If requested MEETING TIME:
BOAT REQUIREMENT: MEETING LOCATION:
DREDGE CUT NAME: Petersons Bar RIVER MILE: MN River 11.8 – 12.6
HISTORIC DATA
Frequency: 60% Avg. Quantity/Job: 18,429 yd3
Last Date Dredged: Sept 27th, 2013 Avg. Quantity/Year: 11,058 yd3
SURVEY DATA
Date Surveyed: September 24th, 2015
Water Surface Elevation: 687.7
Low Control Pool Elevation: 686.8
Net Difference: +0.9’
5 Day River Forecast: Steady Decline
DREDGING DATA
Recommended Channel Width: 100 feet
Recommended Dredging Depth: Cuts 1 & 2: 11 feet, Cuts 3, 4 & 5: 12 feet
Estimated Quantity: 20,149 yd3
Type of Dredge: Contract Mechanical
Proposed Dredging Date: September 30th, 2015
Estimated Duration: 10 dredging days
Justification for Dredging: The navigation channel is closed to the 10.5’ contours.
MATERIAL PLACEMENT DATA
Proposed Placement Site: Cargill East River
Location: MN-14.1-RMP
Site Characteristics: This is an upland beneficial use stockpile site provided to the Corps by the Lower MN River Watershed District.
If you have any questions concerning this project or want to request an on‑site meeting please call me at (651) 324-2050.