DN 18-15 DREDGING NOTICE
U.S. ARMY CORPS OF ENGINEERS
ST. PAUL DISTRICT
NOTICE DATE: July 24th, 2018 DREDGING CATEGORY: Imminent
MEETING DATE: If requested MEETING TIME:
BOAT REQUIREMENT: MEETING LOCATION:
DREDGE CUT NAME: Upper Approach to LD 7 RIVER MILE: 702.5 – 702.8
HISTORIC DATA
Frequency: 13 % Avg. Quantity/Job: 10,150 yd3
Date Last Dredged: August 16th, 2017 Avg. Quantity/Year: 1,269 yd3
SURVEY DATA
Date Surveyed: July 18th, 2018
Water Surface Elevation: 638.7
Low Control Pool Elevation: 638.5
Net Difference: +0.2
5 Day River Forecast: Holding Steady
DREDGING DATA
Recommended Channel Width: 300
Recommended Dredging Depth: 13 feet
Estimated Quantity: 9,007 yd3
Type of Dredge: Contract Mechanical
Proposed Dredging Date: July 25th, 2018
Estimated Duration: 5 dredging day
Justification for Dredging: Channel has been reduced 210’ between the 10.5’ contours and 290’ between the 9’ contours.
MATERIAL PLACEMENT DATA
Proposed Placement Site: Dakota Island
Locations: 7-706.5-RMT
Site Characteristics: This is a historically used temporary island site.
If you have any questions concerning this project, or if you would like to request an on‑site meeting, please call a dredging manager at (651) 290-5155.